Asset: Findhorn Bridge, Scotland'
Benefits: The containment system was heated to allow coating application in lower temperatures.
Engineering: 2kN/m2 UDL
Scope: Access for coating application to two outermost beams.
Location: Underdeck
Operator: Transport Scotland
75% Time Savings Compared to Scaffolding
Description
Work platform required for coating application to the two outermost beams on road bridge. The V-Deck™ design only provided a platform under each of the outermost beams unlike the scaffolding solution which had been to scaffold the entire underdeck of the bridge. V-Deck™ was stepped to follow the curve of the bridge. Encapsulation was part of the VTS design.