Back
Underdeck Solution
Arching

Summary
Asset: Spey Bridge
Benefits: 65% Time Savings Compared to Scaffolding.
Engineering: 2kN/m2 UDL
Scope: 4 Level Solution for concrete repairs
Location: Underdeck
Operator: Transport Scotland
65% Time Savings Compared to Scaffolding
Description
A four level access platform was required for concrete repairs to arch bridge. The platform visible in the photos is the lowest of the four levels. The other levels were installed internally. An installation rate of 5.8m2 per hour was achieved on this project, including the time to install the bolts.'