Asset: Onyx Power Station
Benefits: 2.2t of V-Deck™ compared to 120t of scaffold
Engineering: 1kN/m2 UDL
Scope: Fabric maintenance using V-Deck™ and cradles
Location: Under the hanging coils at top of 76m high boiler
Operator: Onyx
95% Time Savings Compared to Scaffolding
Description
Access was required for works at the top of the 76m high power station boiler. A combination of a two level V-Deck™ and V-Cradle™ was used alongside rope access for a total access solution. The small amount of lightweight V-Deck™ was transported up in the lift, speeding up the project'