Back
Lifting & Lowering Conductor Access
Multi-Level


Summary
Asset: Stag
Benefits: 97% time saving compared to scaffolding.
Engineering: 58m2 engineered to 1.5kN
Scope: Client required a third party work platform to get access to the conductors for remediation down to water level.
Location: Conductors
Operator: Jadestone Energy
Reference
Adaptable & Resilient
97% time saving compared to scaffolding.
Description
The standard scaffold solution would have been a 17 level scaffold that would have been at risk from the incoming cyclone season. The V-Deck™ solution was a 4 level system that could be lifted and lowered in order to mitigate against damage from cyclones. The system was lifted and retracted (see photo) in one shift when a cyclone approached.